PECO Intends To Terminate Interconnection Agreement & Community Renewable Energy Facilities That Provide Insufficient Information

Dockets: FC1171
Category: Uncategorized

Pepco filed a letter of intent to terminate the interconnection agreement from distribution systems and community renewable energy facilities who provided insufficient information.  

On July 16, 2024, Pepco filed CREF biweekly report.

On July 15, 2024, Pepco filed CREF data access agreement and summary of the tech meeting held July 8, 2024.  

As background, OPC filed a complaint against Pepco for alleged violations related to the Community Renewable Energy Facilities program. Specific allegations include:

  • providing erroneous bills to CREF subscribers;
  • providing untimely and incorrect allocation reports to subscriber organizations;
  • installing its own meters on CREFs that report different output than the production-grade meters that are used to calculate RECs;
  • failing to account for, and appropriately pay for, unsubscribed CREF energy; and
  • issuing bills to CREFs that appear to be net energy bills

PECO Letter  (07/25/2025) 
PECO Bi-Weekly Report  (07/16/2024)
PECO Data Access Agreement And Summary Of The Tech Meeting  (07/15/2024)
FC1171 (formerly GD-2022-01-E)
Formal Case No. 1171, In The Matter Of The Investigation Into Community Renewable Energy Facility Practices In The District