PUC Staff and Consultant Respond to Utilities Minimum Stay and TOU Questions
On April 6, 2026 the Maine PUC posts Staff’s and Consultant’s responses to questions from the electric utilities regarding the implementation of the time of use (TOU)…
On April 6, 2026 the Maine PUC posts Staff’s and Consultant’s responses to questions from the electric utilities regarding the implementation of the time of use (TOU)…
On March 13, 2026 in its inquiry into Multi-Year Rate Plans for Investor-Owned Transmission and Distribution Utilities the Maine Public Utility Commission (PUC) issued…
Practice and Procedure, PF Land LLC filed a petition for advisory ruling and request for expedited consideration from the Maine Public Utility Commission “confirming…
The Maine Public Utilities Commission issued an order formally expanding the scope of the time-of-use (TOU) investigation to include additional rate designs that could…
In a press release the Maine Public Utilities Commission PUC accepted bids for Standard Offer electricity supply that set new rates for residential and business…
In Maine, Final Bids for 50% of residential and small non-residential, 100% medium non-residential, and 100% large non-residential for Versant-BHD due by November 18,…
In Maine a case conference was announced and held on October 28, 2025. Central Maine Power (CMP) filed clean and redline revisions to terms and conditions for Sections…
Comments on CMP utility’s proposal were due on October 28, 2025. Previously on October 14, 2025 the Maine PUC issued a procedural order seeking comments on CMP’s…
The Maine Public Utility Commission (PUC) issued order suspending CMP’s requested revision to Section 55 – “Small Generator Interconnection Procedures” for 12 months…
“By this Order, the Commission approves Central Maine Power Company’s (CMP) and Versant Power’s (Versant) proposals to return excess funds associated with certain…
Copyright © 2026 MAGNIFYI®, All Rights Reserved Privacy Policy | Terms of Use