ComEd proposed changes to new service requests for large demand project applicants or customers
ComEd proposed changes to new service requests for large demand project applicants or customers
On May 7, 2026 an Administrative Law Judge (ALJ) issued a Memorandum to the Commission denying JNGO request clarification of the Final Order regarding the
On March 19, 2026, the Illinois Commerce Commission issued a Final Order approving Commonwealth Edison (ComEd) tariff revisions for large load customers. A
In a press release the Illinois Commerce Commission (ICC) announces plans to open an investigation into how ComEd should balance critical issues and cost r
ComEd Reply – ComEd argues that “reopening the record to address this Order is both unnecessary and likely to harm Illinois customers.” Constellation