Reply Comments Filed Re: Utility Rate Increases Standard Filing Requirements
Parties filed reply comments with the Public Utilities Commission of Ohio (PUCO) on the standard filing requirements for utility rate increases. As backgro
-
Duke Energy SOS Procurement Auction Results Filed
A redacted version of Duke Energy’s procurement auction results was filed. The tranche-clearing price for the delivery period of 6/1/26–5/31/27 is $97.47/M
-
Ohio | Electric | Gas | License Revoked | RPA Energy | Supplier | Supplier Violations
Court Affirms PUCO’s Order Rescinding RPA’s Operating Certificates
In re. RPA Energy, Inc., Slip Opinion No. 2026-Ohio-563 – Excerpts from Slip Opinion No. 2026-Ohio-563: {¶ 1} “Appellee, the Public Utilities Commiss
-
Ohio | AEP Ohio | Data Centers | Large Loads | Mark Your Calendar | Supplier | Utility
Technical Conference Scheduled to Discuss AEP Ohio’s Proposal to Manage Default Service for Large Load Customers
To assist the Ohio Public Utilities Commission with its review of AEP’s application and request for interim relief , the administrative law judge (ALJ) is
-
Renewable Energy/Clean Energy | Electric | Legislative Report | Ohio | Renewable Portfolio Standard (RPS) | Supplier | Utility
PUCO RPS Report Sent to the General Assembly for the 2024 Compliance Year
The Public Utilities Commission of Ohio (PUCO) issued an entry directing that the 2024 Renewable Portfolio Standard Report be submitted to the Ohio General
-
Ohio | FirstEnergy | License Applications | PJM | ResCom | Supplier | Utility
PUCO Approves Termination of Supplier Coordination Agreements Between Utility and ResCom for Supplier Default at PJM
On February 18, 2026 PUCO approves entry granting the electric utilities requests submitted to terminate the supplier coordination agreements between the F
-
PUCO Approves SOPEC’ Power Broker Application
The Public Utilities Commission of Ohio (PUCO) grant Southeast Ohio Public Energy Council d/b/a Sustainable Ohio Public Energy Council (SOPEC) an electrici
-
Ohio | AEP Ohio | Duke Energy | NextVolt Energy | Notice of Default | PJM | ResCom | Supplier | Supplier Violations
Two Electric Utilities File Notice of Default Letters for ResCom Energy
Duke Energy filed a notice of default letter that the utility had “received a notice on February 11, 2026, from PJM Interconnection LLC (PJM) stating that
-
Ohio | Broker | Electric | EnergySage | License Applications
EnergySage Files an Electric Broker Application in Ohio
EnergySage, Inc. has filed an electric broker application with the Ohio Public Utilities Commission. The application indicates the company plans to serve r
-
EnergySage Files an Electric Broker Application in Ohio
EnergySage, Inc. has filed an electric broker application with the Ohio Public Utilities Commission. The application indicates the company plans to serve r