Customer Complaint Alleges REP Contract Violates State Business Code
“As a Texas-based utility supplier and a Texas located utility service address for the consumer, Texas contract law should apply. Under Texas Business and
-
Customer Complaint Filed Against REP For Using Photo/Facial Recognition In Enrollment Verification Process
Excerpts from Customer Complaint: “Complainant requests discovery into Respondent’ s practices that are relevant to this complaint. Specifically: (i)
-
TPUC Staff File Updated Estimate Of Installed Generation Capacity In ERCOT
From Staff Report: “The attached Excel spreadsheet provides Staff’ s estimate of the installed generation capacity in the Electric Reliability Counci
-
Utilities File Energy Efficiency Reports Including Information Re: Residential REP Connected Thermostat MTP Program
The utilities presented Energy Efficiency Plan and Reports (EEPRs) to comply with Public Utility Commission of Texas (Commission) 16 TAC §25.181, §25.182 a
-
Bills to Watch
HB3157 – Relating to interim rates charged by electric utilities during a rate suspension period. The bill would require that TDUs must provide retai
-
Reminder – REP Reports
Pursuant to 16 Tex. Admin. Code (TAC) § 25.107(i)(3), the Public Utility Commission of Texas (PUCT) has established Project No. 57398 for the purpose of co
-
Commission Approves Settlement Between Staff And REP
Excerpts from the Public Utilities Commission of Texas (PUCT) Order: {***} “This Order addresses the agreement between Commission Staff and Good Charlie &a
-
PUC Moves ADER Stakeholder Pilot To ERCOT
At the agenda session, the TPUC adopts staff’s February 6, 2025, recommendation to move ADER stakeholder pilot process to ERCOT. Staff Recommendations On A
-
Amended Rule Adopted Requiring TDUs To Maintain Online Outage Tracker With Detailed Information About Power Outages
{***} “The Public Utility Commission of Texas (commission) adopts amendments to 16 Texas Administrative Code (TAC) §25.52 relating to Reliability and Conti
-
Staff Recommends ADER Pilot Program Move To ERCOT Stakeholder Process
Excerpts from Public Utilities Public Utilities Commission of Texas (PUCT) Staff Recommendations: {***} “Staff Recommendation: Much has been learned over t