- The bill creates a competitive framework, administered jointly by NJBPU and the NJEDA, for the State to procure at least 1,100 MW of new nuclear generation.
- Within 180 days (by March 10, 2027) – NJBPU opens request for expressions of interest. Developers have 60 days to submit proposals with regulatory, environmental, financial, and workforce information.
- Next 90 days (by June 8, 2027) – Provisional qualifications. NJBPU qualifies projects to enter the negotiation period or denies them.
- Next 12 months (by June 8, 2028) – Negotiations and stipulations. NJBPU and NJEDA negotiate with project entities including setting accurate cost estimates, price of electricity, and other terms.
- Next 90 days (before September 6, 2028) – NJBPU issues Final Board Order if project provides a net benefit to ratepayers, costs are not unreasonable or excessive in light of customers’ overall bills, and the developer has secured federal financing.
- Ratepayers pay nothing during construction. Once the plant is delivering power, suppliers purchase Reliable Capacity Credits (RCCs) at a fixed negotiated price, instead of volatile market prices
|