PUC Staff Seek Comments On Ancillary Services Costs In Fixed-Rate Retail Contracts

Dockets: 59997 ,Texas
Category: Texas

On November 5, 2026 PUCT Staff issued a notice that it seeks comments on the treatment of DRRS and other future ancillary services costs in existing fixed-rate retail contracts.

As background, on July 1, 2026, the Texas Retail Electric Provider (REP) Coalition filed comments regarding Nodal Protocol Revision Request (NPRR) 1309, which developed the Dispatchable Reliability Reserve Service (DRRS) as a new ancillary service. Specifically, Texas REP Coalition asked that the order approving the NPRR include language designating DRRS as an ancillary service product incurring charge beyond a REP’s control for a customer’s existing contract. Under 16 TAC § 25.475(b)(5), a fixed-rate price may not vary to reflect changes in ancillary service charges unless the Commission makes such a designation. Texas REP Coalition requested the designation apply to customer contracts existing prior to DRRS’ s inclusion in the ERCOT Ancillary Services Plan.

The Commission approved NPRR1309 on July 9, 2026, without the requested designation. The Commission instead directed Commission Staff to open a project to gather feedback and consider what guardrails may be needed before any future consideration of such designations.

Now, Staff seeks comment regarding the existing rule that allows a REP -after a PUC designation- adjust an existing fixed rate due to an ancillary service product under which the REP incurs costs beyond the REP’s control.  In addition, Staff also seeks comment on ERCOT’s new Dispatchable Reliability Reserve Service (DRRS).

Consistent with this direction, Commission Staff requests responses to the questions posed below:

Part 1: DRRS Costs

In any evaluation of whether DRRS costs are within or beyond a REP’s control? -What factors should the Commission consider? -When should control be deemed established? -What circumstances, if any, would prevent a prudent REP from managing DRRS costs through hedging and other risk management practices?

If the Commission were to designate DRRS as an ancillary service incurring charges beyond a REP’s control under §25.475(b)(5), therefore allowing a fixed rate price to vary for existing contracts. -What should be the mechanism to effectuate the price variation? i. One-time adjustment; or ii. Recurring pass-through.  How should the adjustment or pass-through amount be quantified? What specific formula should a REP use to calculate the amount billed to each customer? – What should be the timing of the adjustment or pass-through? -To whom, and how, should notice be provided of the adjustment or passthrough? -What additional customer protections should be ordered?

Part 2: Process

Should the Commission amend its rules to do one of the following, and if so, why?: -Repeal the relevant language in §25.475(b)(5), to eliminate the avenue through which a REP could change the price of an existing fixed-rate contract to reflect ancillary service costs; or -Clearly define a process for considering and authorizing variations to existing fixed-rate contracts to reflect the cost of a new ancillary service.

If the Commission’s rules continue to provide some avenue for a REP to vary the price of existing fixed-rate contracts to reflect the cost of a new ancillary service:

What regulatory process is appropriate? i. Contested case initiated by REPs; ii. A determination the Commission makes at a defined point for each new ancillary service; or iii. A rulemaking or other proceeding that establishes criteria in advance to guide the Commission’s determination (e.g., a required showing, trigger date, guardrails on the amount or duration of an adjustment). -What standard should the Commission apply before allowing variation to existing fixed-rate contracts? Is the “beyond the REP’s control” standard sufficient by itself? -What is the appropriate timing for the Commission to make such determinations? -To whom, when, and in what manner should notice of a possible price variation be provided?

If the Commission were to amend its rules to more clearly define a process for considering and authorizing variations to existing fixed-rate contracts, should any future designation regarding DRRS: -be held until the rule amendments are effective and processed under the new rules; or -be decided under an interim process.