Staff Proposes Bring Your Own Load Generation Option

Dockets: Maryland ,PC72

In response to the September 15, 2026, Notice of Procedural Schedule, Maryland PSC Staff filed revised comments in the large load tariff proposal.

In Staff’s most recent revision is proposing that electric utilities should have the option to require large load customers to Bring their Own New Generation (BYONG).

Staff’s proposed BYONG option provides the utility an alternative to requiring the large load customer to pay any increase in PJM wholesale market non-transmission costs caused by the large load customer.

If the utility elects to require BYONG option under staff’s proposal, the Large Load Customer shall demonstrate BYONG sufficient for the load ramp period, plus the first 10 years of an initial contract term for delivery service from the utility.

Staff specifically proposes “Large Load Customer contracted BYONG resource or resources shall be projected to provide, on an annual basis, at least 90 percent of the Large Load Customer’s forecast load and load ramp schedule.”