ALJ Approves Utility’s Distribution Cost Recovery Factor

Dockets: 59981 ,Texas

Texas PUC ALJ issued an order approving an unopposed motion from CenterPoint Energy Houston Electric, LLC to implement its proposed increase in CEHE’s Distribution Cost Recovery Factor (DCRF) on an interim basis.

“The Administrative Law Judge grants the motion and authorizes CenterPoint Houston to implement, on an interim basis, the requested rates, which are included as exhibit A to the motion, effective for usage occurring on and after September 30,2026, subject to surcharge or refund in accordance with 16 Texas Administrative Code § 22.125 if the interim rates differ from the rates ultimately approved by the Commission.”

The interim rates, listed below, will be effective for meters read on and after September 30, 2026

The interim rates will be charged until a final approved tariff resulting from CEHE’s DCRF application becomes effective, and are subject to reconciliation to the extent the interim rates differ from the final tariff rates

CenterPoint Energy Houston Electric

Rider DCRF

Distribution Cost Recovery Factor

Current            Interim  For Usage On & After 9/30/26

Residential

$ per kWh          $0.004944    $0.006137

Secondary <= 10 kVA

$ per kWh          $0.004508    $0.005490

Secondary > 10 kVA

$ per billing kVA  $0.796213    $1.008963

Primary

$ per billing kVA  $0.371995    $0.500784

Transmission

$ per 4CP kVA      $0.009819    $0.012172

Lighting

$ per kWh          $0.084803    $0.108003