On November 10, 2026 an Administrative Law Judge (ALJ) issued a scheduling order in PPL’s petition in PPL’s sixth Default Service Plan (DSP VI) for the period June 1, 2025 through May 31, 2029.

The ALJ’s order, granted petitions to intervene filed by multiple stakeholders, including retail No CAUSE-PA, REI, Environmental Intervenors, Amazon, Citizens, RESA, Governor Josh Shapiro, Constellation, PPLICA, KEEA, DCC, Erika Cook, or John Zola.  The petitions to intervene were granted.

The order also approved PPL’s request to consolidate four (4) related proceedings (Docket Nos. P-2026-3065185, P-2026-3065186, P-2024-3047290 and C-2026- 3065756) are consolidated) and dismissed the motion to waive the 9-month deadline for reviewing its default service plan as moot after PPL voluntarily agreed to extend the deadline without objection.

As background PPL’s petition sought approval of: (1) the Company’s proposed non-bypassable Customer Protection Transmission Rider (CPTR) to recover all Network Integration Transmission Service (NITS) costs and certain other transmission costs and to allocate certain network upgrade costs to Rate LP-6; (2) the elimination of the Transmission Service Charge (TSC); (3) changes to the Generation Supply Charges to include the costs currently recovered under the TSC that will not be recovered through the CPTR, along with the associated net over or undercollection balance; (4) the proposed amendment of PPL’s existing Default Service Program and Procurement Plan (DSP VI) to incorporate the programmatic and process changes to implement the non-bypassable.