News Stories

Sponsored by Earth Etch. Regulatory insight and compliance solutions for today’s energy markets.

ALJ Sets New Comment Date In AEP Ohio Data & Mobile Center Tariff Matter

Dockets: 24-0508-EL-ATA
Category: Uncategorized

The ALJ ordered that the comment deadline for the filing of both comments and reply comments are amended. Initial comments are now due by June 25, 2024, and reply with reply comments due by July 8, 2024.  

As previously reported, AEP Ohio is seeking approval of tariffs that would create two new customer classifications: (1) the Data Center Power tariff for new data center customers that will use a monthly maximum demand of 25 MW or greater at a single location; and (2) the Mobile Data Center tariff for new mobile data center customers (e.g., cryptocurrency miners) that will use a monthly maximum demand of 1 MW or greater at a single location.

ALJ Order  (06/07/2024)
24-0508-EL-ATA (Opened 05/13/2024)
In the Matter of the Application of Ohio Power Company for New Tariffs Related to Data Centers and Mobile Data Centers