Comment Period Established in Resource Adequacy Rulemaking
On November 20, 2026 a tentative order is scheduled for publication in the Pennsylvania Bulletin on 11/21/26 in the electric distribution company interim resource adequacy service, pre-emergency and emergency response provisions.
This tentative order triggers a 30-day comment period, followed by a 15-day reply comment period.
On October 1, 2026, the Pennsylvania Public Utility Commission (Commission) entered a Tentative Order at the above-captioned docket seeking comments on a proposed requirement that all electric distribution companies (EDCs) update their pre-emergency and emergency load control procedures to incorporate Interim Resource Adequacy Service (IRAS) and to ensure that data centers are not classified as critical load exempt from curtailment during these events. In addition, the PUC sought comments on the implementation of a PJM Interconnection, L.L.C. (PJM) Tariff filing with the Federal Energy Regulatory Commission (FERC) regarding its proposed IRAS to address the rapid energy demand growth imposed by new large load data centers.1 Due to FERC’s recent decision on PJM’s proposed IRAS framework and a Bring Your Own New Capacity (BYONC) pathway for New Large Loads of 50 megawatts (MW) or greater, the Commission is clarifying the scope of its October 1st Tentative Order and modifying the previous timeframe for filing initial comments and replies.
As background, on July 14, 2026, PJM announced that its most recent Base Residual Auction (BRA) cleared short of its reliability requirements resulting in a 6,831 MW capacity shortfall for the 2028/2029 Delivery Year. Subsequently, on August 13, 2026, PJM submitted to FERC proposed revisions to its Reliability Assurance Agreement Among Load Serving Entities (RAA) and to its Open Access Transmission Tariff (Tariff) to establish an IRAS to address the rapid energy demand growth imposed by new large load data centers.
Also aa reminder the Pennsylvania PUC passed a motion directing Staff to propose updates to emergency electric load control regulations, including “greater clarity regarding the order, criteria and circumstances under which customers may be curtailed during pre-emergency and emergency conditions.”