MT PSC Issued Procedural Order in Northwestern Energy Rate Case
Intervenor testimony due by 1/17/25; NEW rebuttal testimony and cross-intervenor testimony due by March 14, 2025.
Any settlements, supporting testimony, and workpapers due by March 24, 2025.
Non-settling party testimony regarding any settlements due by April 9, 2025.
Prehearing memoranda due by 4/16/25; objections to prehearing memoranda due by April 18, 2025. Hearing scheduled to begin April 22, 2025.
Procedural Order. (09/18/2024)
MTPSC Docket No. 2024.05.053 (Opened 05/07/2024)
Northwestern Energy (NWE) Petition For An Increase In Electricity And Natural Gas Rates.