News Stories

Got a tip or story? Share it with MAGNIFYI®.


Parties File Standard Rate Offer Stipulation Agreement and Data Center Proposal

On November 5, 2026 AES Ohio and several stakeholders filed a stipulation recommending that the Public Utilities Commission of Ohio (PUCO) approve AES Ohio’s proposed market rate offer (MRO), effective June 1, 2027, replacing its existing electric security plan.

Signatory parties include Dayton Power And Light Company D/B/A AES Ohio, Staff Of The Commission, Office of the Ohio Consumers’ Counsel, Ohio Energy Group, Ohio Manufacturers’ Association Energy Group, City of Dayton, Ohio Energy Leadership Council, Google, Interstate Gas Supply, Constellation Energy Generation, Constellation NewEnergy, and Retail Energy Supply Association (RESA).

The agreement maintains AES Ohio’s competitive bidding process for standard service offer (SSO) generation while establishing a separate tariff class and hourly-priced default service procurement auction for data centers with demand exceeding 25 MW.

AES Ohio shall continue its current Standard Offer Rate and CBP, subject to the modifications in the Direct Testimony of Hani Jaber and the Direct Testimony of Robert Lee filed in these proceedings, which reflect the creation of a separate Data Center1 tariff class for SSO service and a new auction for the procurement of generation supply for Data Center customers taking SSO service. AES Ohio shall have authority to defer and recover exclusively from Data Center customers up to $75,000 in non-legal consultant fees relating to the development of the new auctions for Data Center customers reflected in the Application. Data Centers shall pay all costs associated with 1) the creation of the separate Data Center tariff class for SSO service, and 2) the creation, administration, and operating of any auction for the procurement of generation supply for Data Center customers taking SSO service.

Hourly Price Service shall reflect a pass-through to the Data Center Tariff customers supplied with this product of all energy, capacity, ancillary costs, and any other costs imposed on an SSO Supplier in providing the Hourly Price Service to the Data Center Tariff customer, including but not limited to any costs assigned by PJM under the proposed Reliability Backstop Procurement (“RBP”) process. Data Center Tariff customers receiving Hourly Price Service shall likewise be responsible for making the Hourly Priced Variable Payments reflecting these costs.

Data centers would bear the costs of their separate procurement arrangements, including applicable PJM reliability-related charges, to prevent cost shifting to other customers.

The stipulation also proposes revised emergency electrical procedures, eliminates the MRO’s fixed expiration date, and requires stakeholder reviews every 2 years. The agreement remains subject to PUCO approval.

AES Ohio shall operate under its current Electric Security Plan, as approved by the Commission in Case No. 22-900-EL-SSO, through May 31, 2027. The Company’s Market Rate Offer, as approved in this proceeding, shall commence June 1, 2027.

On November 5, 2026 ALJ granted the motions to intervene and established an 11/9/26 deadline for testimony supporting the stipulation. The hearing remains scheduled for 11/12/26.

As background, as originally filed AES Ohio (Dayton Power & Light) filed an application to implement a new market rate offer (MRO) for default service, including a separate SSO procurement for data centers. Under the proposal, all data center customers would share the administrative costs of the separate data center auction, including customers taking competitive retail supply. For shopping data centers, these costs would be recovered through a flat per-customer charge. Data center default service would be priced based on hourly PJM prices plus an adder established through a competitive auction. For other SSO customers, AES Ohio proposes to continue its existing competitive procurement structure using twice-annual auctions and a mix of 12-and 24-month full-requirements contracts, with procurements extending through 5/31/32.  Extensive testimony and meetings have been held that resulted in the filed stipulation.