Staff Files Comments on Recommended Framework for Net Metering

Dockets: Maryland ,PC78

On November 10, 2026 Commission Staff of the Maryland PSC filed comments on the Recommended Framework for Net Energy Metering Successor report (“Successor Report”) filed on October 27, 2026.

Staff’s comments focused on four specific recommendations of the report, (1) the recommendation to phase in the Net Energy Metering (“NEM”) 2.0 program, (2) the use of a surcharge to recoup costs from NEM customers, (3) the compensation level of NEM 2.0, and (4) the treatment of Community Solar Energy Generating Systems (“CSEGS”) and their subscribers.

Phase-In of NEM 2.0

“Staff does not agree with the report’s recommendation to phase in the NEM 2.0 program. The Successor Report supports the decision to phase in NEM 2.0 for two main reasons: first, the PUA requirement to implement the successor program by July 1, 2027, and second, the feedback from the utilities, which noted that design options for NEM 2.0 could take months or years to implement.

The phased-in approach will confuse customers and result in different compensation levels for NEM customers depending on when they interconnected their NEM system. This may also cause complications for utilities because their billing systems will need to identify when various NEM customers became NEM customers to compensate them appropriately, because, as noted in the report, “Projects qualified to participate in Phase I would remain on this design for the life of the project.”8 Therefore, utility billing systems will need to identify at a minimum three different types of NEM customers, if not more. Staff recommends that no phase-in of NEM 2.0 be used because it will cause more confusion and complications than implementing a new successor program at once. As noted above, the phase-in is also supported by feedback from utilities that do not believe they can address any changes other than a non-bypassable surcharge by July 1, 2027.”

Non-Bypassable Surcharge

“The Successor Report supports the use of the surcharge because the consultant team believes that the surcharge is, “the only design that can be implemented for all project types by July 1, 2027.”9 Staff does not hold this same opinion. Staff does not understand how simply providing less compensation on a customer’s bill for NEM would be any more difficult to implement than an entirely new surcharge. The utilities have not provided conclusive evidence that a surcharge is the only option that can be implemented by July 1, 2027

The Successor Report also notes that “Introducing a non-bypassable surcharge is likely the simplest and easiest to explain of the options considered.” 11 Staff disagrees with this sentiment. In Staff’s view, adding a surcharge to a customer’s bill is not the simplest or easiest option to explain to customers. Whenever a utility adds a new surcharge to customer bills, customers will invariably have questions about it. Customers may view the surcharge as punitive and may believe they are incurring additional charges because they are a NEM customer. Staff believes that it would be easier and simpler to explain a reduced compensation level to customers, since there would be no additional charges on their bill. In this case, a NEM customer would have no reason to believe they are being charged additional rates and or fees for being a NEM customer.

If the Commission accepts the surcharge, Staff has no concerns using the method, as proposed by the consultants, which calculates the surcharge based on the size of the customer’s NEM system in kW. 12 Staff believes this is the simplest way to determine the impact each NEM customer has and also provides a straightforward calculation which is easy to understand for NEM customers.”

NEM 2.0 Compensation

“The Successor Report notes three options of rates and charges that may be included in any proposed surcharge: EmPOWER retail surcharges only, EmPOWER retail surcharges plus additional charges, and everything but SOS.13 However, the Successor Report made no specific recommendation regarding the level of compensation/surcharge for NEM 2.0 customers but stated, “it is not a part of the Consultant Team’s recommendation at this time that the non-bypassable charge be limited exclusively to the value of those EmPOWER retail surcharges.” 14 Staff agrees that the surcharge should not only include EmPOWER surcharges.”

CSEGS

“For CSEGS Staff supports the Successor Report’s recommendation not to apply the nonbypassable surcharge to CSEGS subscribers and that a reduced value be applied to the subscribers’ bills.”

Read all comments at docket link.