The Maryland utilities continue to submit “do not transfer list” status reports See links for utility specific reports: Pepco | WGL | BGE. Suppliers submitted…
The Maryland utilities continue to submit “do not transfer list” status reports See links for utility specific reports: Pepco | WGL | BGE. Suppliers submitted…
On March 13th WGL and Pepco submitted February 2026 Customer Choice report. Utilities continue to submit “do not transfer list” status reports. See links for…
From Letter: [ *** ] The Commission has reviewed the request filed on June 23, 2025, by Baltimore Gas and Electric Company updating the status of its implementation of…
From Letter: [ *** ] The Commission has reviewed the request filed on June 23, 2025, by Baltimore Gas and Electric Company updating the status of its implementation of…
From Letter: [ *** ] The Commission has reviewed the Do Not Transfer List Automated Enrollment Block filed on June 23, 2025, by The Potomac Edison Company. After…
From Order: [ *** ] On July 19, 2024, the Commission issued a Notice of Implementation of Senate Bill 1 of 2024 (“SB 1”) Do Not Transfer List Requirements.1 The Notice…
In Maryland the PSC issues a notice announcing the initiation of Public Conference 67 and its intent to seek comments. On December 6, 2024, the Commission’s Technical…
BG&E has determined that the existing customer list made available to suppliers will no longer be appropriate. From BG&E Response: [ *** ] After reviewing the…